Backcast test · canonical clock · floor 10

House on the sundial

A four-bedroom detached house in the West Midlands, planned backwards from the keys. Each of 455 jobs sits at the smallest period that contains it on the clock, and ten hands hold their commitments at the same addresses.

Planned workDone, as at the hand Critical chainProject bufferPast the keys date ◆ state reached · ◇ state to come

Programme strip

Buffer against chain

Keys across 200 simulated builds

Rung fit of the 399 crew jobs

How the spine was made

    What the test shows

      Four traditions on one ladder

      Sources: Robinson, backcasting (1982); the prerequisite tree in Goldratt's thinking processes; Ballard, The Last Planner System of Production Control (University of Birmingham, 2000); the five conversations; buffer sizing in critical chain; inspection stages from a council building control page. The house, its durations and the 200 builds are a model, not a real site.